Enlight Renewable Energy is an Israeli renewable-energy company that develops, finances, builds, owns, and operates utility-scale solar, wind, and energy-storage projects. Founded in 2008, it grew from Israeli photovoltaic installations into an international business spanning Israel, Europe, and the United States, with a model that covers projects from development through operation. Its portfolio includes the Genesis Wind project in the Golan Heights and solar facilities paired with battery storage; it has also pursued projects with partners in the Middle East and North Africa. Enlight’s expansion has brought it into public markets and into debates over land use and the environmental effects of wind power.

02Overview

Enlight Renewable Energy is an Israeli renewable-energy company headquartered in Rosh Ha’ayin. It develops, finances, constructs, owns, and operates utility-scale solar, wind, and energy-storage projects, acting as both a developer and a power producer.[1][2] Its shares trade on the Tel Aviv Stock Exchange and Nasdaq under ENLT, and its portfolio spans the United States, Europe, and Israel.[1][2]

03Origins and Corporate Development

Enlight was founded in Israel on August 6, 2008, by Gilad Yavetz, Zafrir Yoeli, and Amit Paz. It initially developed small-scale greenfield solar projects in Israel. Its Form 20-F lists the start of onshore wind-energy development in 2011 as a later milestone in its expansion beyond solar power.[2]

In 2009, Enlight won a build-operate-transfer project involving 25 rooftop photovoltaic installations on industrial farm buildings around Israel. The reported plan called for Enlight and its partners to finance construction, lease rooftops from their owners, and sell the electricity to Israel Electric Corporation under 20-year power-purchase agreements. Enlight was to serve as the engineering, procurement, and construction contractor and operate and maintain the systems for 20 years. Intended locations included the Golan Heights, Jezreel Valley, Carmiel, Arad, and Beersheva.[3]

The company merged in 2010 into Sahar Investments Ltd., which changed its name to Enlight Renewable Energy Ltd. on August 4, 2010. Enlight’s shares have traded on the Tel Aviv Stock Exchange since February 2010 under the symbol ENLT.[2] A contemporary retrospective put the valuation of its 2010 public listing at NIS 59 million, approximately $17.3 million at the time.[4]

Enlight’s growth included larger solar and wind developments in Israel. In 2015, it and the Noy Infrastructure and Energy Investment Fund built the Halutziot photovoltaic field in the Western Negev. The reported project had 55 megawatts (MW) of capacity, cost NIS 500 million, covered 800 dunams, and contained 180,000 solar collectors. It was a regional venture involving land belonging to communities including Naveh, Benei Netzarim, Ohad, and Dekel.[5]

The company listed on Nasdaq in February 2023 while continuing to trade in Tel Aviv. Its ordinary shares began trading on the Nasdaq Global Select Market on February 10, 2023.[2] Globes reported that Enlight’s Nasdaq offering priced 14 million shares at $18 each, raising $252 million and valuing the company at about $2 billion.[6] The Jewish Virtual Library lists the company under ENLT and classifies its sector as wind and solar energy.[7]

04Practice and Technologies

Enlight’s business covers the development, financing, construction, ownership, and operation of utility-scale renewable-energy projects. Its technologies include solar power, wind power, and energy storage, and its stated operating model extends from greenfield development and design to finance, construction management, asset management, and ownership.[1] In practice, projects can combine generation with storage, allowing the company to develop both electricity-producing facilities and systems that store energy.

The company primarily earns revenue by selling electricity through long-term power-purchase agreements (PPAs) with electricity authorities, utilities, and corporations. Enlight’s Form 20-F describes typical PPA terms of 10 to 30 years; some electricity is instead sold in wholesale markets without a long-term contract or committed buyer. The filing says the company uses short-term hedging to manage some exposure to those merchant-market sales.[2]

The project pipeline is divided into stages that indicate how close a project is to construction or operation. In its 2024 Form 20-F, Enlight defined Mature Projects as operational, under construction, or in pre-construction with construction expected to begin within 12 months. Advanced Development Projects were expected to start construction within 13–24 months, while Development Projects were not expected to begin within 24 months.[2] As of February 19, 2025, the company reported about 6.1 gigawatts (GW) of generation capacity and 8.6 gigawatt-hours (GWh) of storage capacity in its Mature Projects category.[2]

Enlight’s portfolio webpage lists 6.2 GW of generation and 10.35 GWh of storage in Mature Projects, 2.64 GW and 11.63 GWh in Advanced Development, and 11.16 GW and 31.45 GWh in its Development pipeline. The page gives no as-of date for these figures, so they should not be read as a dated update or directly reconciled with the filing’s earlier totals.[8] Enlight describes Mature Projects as providing cash flow from operating assets and near-term growth visibility from projects under construction, in pre-construction, or contracted under signed PPAs.[8]

05International Expansion and Operations

Enlight expanded beyond Israel through a sequence of European market entries and, later, its move into the United States. Its Form 20-F lists a first European solar project in 2012, entry into European wind markets in 2014, expansion into the Balkans in 2016, and entry into Hungary’s solar market in 2017. It entered the United States in 2021 through the acquisition of Clēnera and had its first operational U.S. project in 2023.[2]

In 2020, Enlight acquired a controlling interest in Sweden’s Björnberget wind project, which was reported to have a total capacity of 372 MW and construction permits. Plans called for 60 turbines. Enlight’s projected share was 55%–61%, with the remaining project interest held by the European Prime Green Energy Investment Fund. Enlight was also reported to receive about 20% of the fund and to invest up to €50 million in it.[9]

In June 2021, Enlight announced that it would acquire 90% of the U.S. renewable-energy company Clēnera at a reported valuation of $433 million. The reported transaction covered 50 large solar projects with combined output of 12 GW and 5.5 GWh of storage. The purchase price included $158 million at closing and up to $232 million in performance-based payments; Clēnera’s founders were to retain a 9.9% minority interest and senior management roles.[10] Enlight’s Form 20-F describes the completed U.S. entry as the acquisition of a 90.1% equity interest in Clēnera, a utility-scale solar and storage developer focused particularly on the western United States, with the founders retaining 9.9%.[2]

As of February 19, 2025, Enlight reported activity across 12 countries on three continents. It identified the United States, Southern Europe, and Israel as its largest markets for in-house greenfield development teams, and said it worked with local co-development partners in smaller markets.[2] An August 2026 report described its operating portfolio across the United States, Europe, and Israel, with generation capacity of 2.9 GW and storage capacity of 3.5 GW. It also expressed the combined assets as approximately 3.9 “factored gigawatts,” a metric combining generation and storage.[11]

The same report said Roadrunner in Arizona and Quail Ranch in New Mexico entered commercial operation at the end of 2025. Roadrunner comprised 290 MW of solar capacity and 940 MW of storage, while Quail Ranch comprised 128 MW of solar and 400 MW of storage. Enlight’s U.S. operating-asset revenue reached $80 million in the second quarter of 2026, compared with $34 million a year earlier.[11]

06Projects in Israel

Enlight’s Israeli projects span rooftop solar, utility-scale solar fields, wind generation, and solar facilities paired with storage. The company’s Genesis Wind project is in the Golan Heights. A 2023 report said commissioning began on the first of 39 General Electric turbines; the project was expected to deliver 207 MW, equivalent to the annual electricity use of 70,000 households, and avoid 180,000 tons of carbon emissions per year.[12] The company describes Genesis as Israel’s largest renewable-energy project and says it has 39 turbines and 207 MW of installed capacity, including expansion.[13]

The Genesis project included eight Golan Heights settlements and Aveeram Ltd. as partners, according to a project report. Its infrastructure included a privately developed 27-kilometer, 161-kilovolt underground transmission cable, described as Israel’s first of its kind, and a privately held substation. Construction was reported to have created hundreds of jobs over three years. The project’s first full operating year was forecast to generate $50–52 million in revenue under a 20-year inflation-linked power-purchase agreement with Israel Electric Corporation.[12]

The first Genesis turbine was commissioned in June 2023, and the project reached commercial operation in October 2023, according to Enlight’s Form 20-F. The filing lists the project at 207 MW, with an approximate 54% Enlight share and an inflation-indexed tariff agreement through 2043.[2] The 27-kilometer cable was intended to connect Genesis and other planned area projects to the national grid.[12]

Enlight also developed solar generation with storage. In August 2023, its Sde Nitzan project began commercial operations with 23 MW of renewable-energy capacity and 40 MWh of storage. It was described at the time as the company’s first project connected to the electricity grid and Israel’s largest project combining solar power and storage. Sde Nitzan formed part of an Enlight cluster planned to reach 248 MW of solar capacity and 474 MWh of storage, with the remaining capacity then expected to connect by the end of the first half of 2024.[14]

In July 2024, Enlight commissioned solar-and-storage projects at Yesha and Re’im in the Western Negev. Together, they provided 16 MW of solar capacity and 94 MWh of storage, and were described as the company’s eighth and ninth integrated solar-storage projects in Israel. They were connected ahead of their original schedule despite the war in Gaza, with reported cooperation from Israel Electric Corporation and security authorities.[15][16]

At that time, Enlight reported nine solar-storage units in Israel and four grid-connected projects in Gaza-border communities since October 2023. It planned to reach 12 Israeli facilities by the end of 2024, with approximately 250 MW of solar capacity and 600 MWh of storage. The company estimated that, together with international partners, 632 MW of generation and 1,880 MWh of storage would operate in an integrated configuration by year-end.[15] These were plans and estimates reported at the time, rather than confirmation that every target was subsequently achieved. A related estimate put the projected first-full-year revenue for the Israeli projects at NIS 128–135 million and EBITDA at NIS 88–93 million, identifying 2025 as the anticipated first full year.[16]

Enlight’s Israeli development has also included a large storage proposal in the southern Arava. In April 2026, it received regulatory approval for a planned 645-MWh facility near Kibbutz Neot Smadar, alongside solar-generation facilities already in the area. The estimated construction cost was NIS 370–400 million. Enlight was seeking a building permit, with construction potentially beginning in 2026 and commercial operation planned for July 2028; the site was to use land belonging to the kibbutz and the Hevel Eilot Regional Council, in cooperation with the kibbutz.[17]

07Regional Partnerships

Enlight has pursued renewable-energy projects with NewMed Energy in the Middle East and North Africa. In 2022, the companies said they planned to jointly develop, finance, build, and manage projects involving solar, wind, and storage, working with local partners. The proposed markets included Morocco, the United Arab Emirates, Bahrain, Saudi Arabia, Oman, Egypt, and Jordan. Enlight was reported to be the controlling shareholder during construction and operation.[18] Those countries and arrangements were described as plans at publication, not as a record that projects had been completed in each market.

A later Institute for National Security Studies article said Enlight and NewMed had “launched a renewable energy project across several Arab countries,” but did not identify the project, specify the countries, quantify its scale, or describe the companies’ respective roles.[19] The available accounts therefore establish a regional partnership and report a project launch, while leaving its particular components and scope unspecified.

The INSS article placed regional environmental cooperation within a discussion of criticism sometimes termed “eco-normalization.” It reported critics’ argument that environmental initiatives can mask or divert attention from Israeli policies, particularly in Gaza. This is an account of critics’ views about such initiatives, not a project-specific finding about Enlight or evidence of the company’s particular role in the criticism.[19]

08Leadership and Financial Performance

Enlight was founded by Gilad Yavetz, Zafrir Yoeli, and Amit Paz. Yavetz later served as chief executive officer, and in 2025 the company appointed Adi Leviatan to succeed him. Globes reported the appointment in July 2025, with the role taking effect on October 1. Yavetz became executive chairman, while then-chairman Yair Seroussi became deputy chairman.[20]

Before joining Enlight, Leviatan led a business division of 3M, managing 700 people worldwide and a business with reported annual revenue of $1.5 billion. Globes also reported that she had prior experience at McKinsey.[20] An April 2026 interview identified her as Enlight’s CEO and reported that the company’s shares traded as ENLT on both Nasdaq and the Tel Aviv Stock Exchange.[21]

The Jerusalem Post reported that Enlight’s 2025 revenue was about $582 million, up 46% from 2024, and that net profit rose 142%, without giving the profit amount.[21] In the second quarter of 2026, Enlight reported revenue of $210 million, up 56% year over year, and adjusted EBITDA of $160 million, up 67%. First-half revenue was $409 million, a 54% year-over-year increase.[11] The comparison of first-half net profit was affected by an $81 million one-time gain in the first quarter of 2025 from selling a 44% stake in the Sunlight project portfolio in Israel to Harel and partners.[11]

At the end of 2025, Enlight agreed to supply electricity to 550 Mivne properties in Israel for 15 years. Globes valued the agreement at about NIS 1.5 billion in total, or approximately NIS 100 million annually. The companies also planned a joint venture to build energy-storage facilities on the properties’ rooftops.[22] In May 2026, Enlight signed a 15-year agreement to supply the full output of its 250-MW Solstice project to Google. The project was expected to begin construction in 2028 and operation in 2029; the reported estimate was about $60 million in annual revenue, dependent on when operations begin.[11]

09Significance and Public Role

Enlight’s Form 20-F identifies project siting, interconnection and transmission access, permitting, construction delays, supply-chain disruption, electricity-price exposure, and changes in renewable-energy policy as business risks. It also says generation and revenue depend partly on meteorological and environmental conditions, and identifies extreme weather, equipment outages, and transmission constraints as potential risks.[2] These factors are relevant to a business whose projects require suitable sites, permits, grid connections, and long-term arrangements for selling electricity.

The filing also discussed risks to Israeli operations during the war following Hamas’s October 7, 2023 attack, including possible effects on employees, infrastructure, shipping, financing, and access to project sites. At the time of the filing, Enlight said the war had not materially affected its operations or financial results, while warning that future effects were uncertain.[2] That assessment is time-bound to the filing and is not a current evaluation of the effects of the war.

Enlight’s public role reflects the growth of Israeli renewable-energy development from early photovoltaic installations into projects combining wind, solar generation, and storage, as well as international partnerships and operations. The company’s filings and project reports document a strategy spanning the full project lifecycle, while its local developments have involved community partners, electricity buyers, and national infrastructure.[1][12] The scale and location of particular projects have also brought environmental and land-use concerns into public debate, especially around wind facilities in the Golan Heights.

10Controversies

Genesis Wind faced opposition from Druze leaders and residents who said the project encroached on their land. In June 2023, Druze leaders called for construction to be frozen during Eid al-Adha, and a report said Prime Minister Benjamin Netanyahu subsequently ordered a temporary pause over the holiday.[23] Enlight said it had invested tens of millions of shekels through local taxes, jobs, landowner payments, and mine clearance, and rejected claims that it had violated residents’ land rights. These are attributed positions; the cited reporting does not independently resolve the land-rights dispute.[23]

Wind development in the Golan Heights has also prompted environmental concerns. A 2022 report said the National Infrastructure Council approved seven additional turbines for Enlight’s Valley of Tears wind farm, although the company had applied for 11. The Society for the Protection of Nature in Israel, backed by the Environmental Protection Ministry, had petitioned against new wind farms over concerns about ecological effects.[24]

The same report described a radar system Enlight had promised to install at Valley of Tears to detect approaching birds and stop turbine blades. Tests reviewed by the Israel Nature and Parks Authority’s chief scientist reportedly found no detection at either the two-kilometer test range or the 600-meter range intended to trigger turbine shutdown.[24] The report also discussed broader concerns about bird and bat mortality around turbines and monitoring findings at other Israeli sites. Those other-site results are not measurements from Genesis Wind. Enlight says it installed a Radar Assisted Shut Down On Demand system at Genesis to protect the Golan Heights vulture population.[13]

The Golan Heights is described differently in sources discussing political status. A 2022 Times of Israel report characterized it as territory Israel captured from Syria in 1967 and annexed in 1981.[24] Enlight’s Form 20-F notes that some of its projects are there and that the United States recognizes Israeli sovereignty over the Golan Heights while the European Union does not.[2] These differing descriptions form part of the context surrounding projects in the area; the cited reporting does not settle the political dispute.

Sources

  1. 1Enlight Renewable Energy, Sustainable Energy, accessed on October 23, 2026.
  2. 2Enlight Renewable Energy, Form 20-F, accessed on October 23, 2026.
  3. 3Globes, Enlight to build new nation-wide solar energy project, accessed on October 23, 2026.
  4. 4CTech by Calcalist, Renewable energy company Enlight going public on Nasdaq at over $2 billion valuation, accessed on October 23, 2026.
  5. 5Globes, Israel's largest solar field inaugurated, accessed on October 23, 2026.
  6. 6Globes, Enlight completes $252m Nasdaq offering, accessed on October 23, 2026.
  7. 7Jewish Virtual Library, Israel Business & Economy:Israeli Stocks Traded on Wall Street, accessed on October 23, 2026.
  8. 8Enlight Renewable Energy, Our Portfolio, accessed on October 23, 2026.
  9. 9Israel Hayom, Israel’s Enlight now controls one of Europe’s biggest wind farms, accessed on October 23, 2026.
  10. 10Globes, Israel's Enlight acquires US renewable energy co Clenera, accessed on October 23, 2026.
  11. 11CTech by Calcalist, Google deal and US projects send Enlight’s revenue soaring as renewable energy company raises forecast, accessed on October 23, 2026.
  12. 12Globes, Israel's biggest renewable energy project begins operation, accessed on October 23, 2026.
  13. 13Enlight Renewable Energy, Genesis Wind Project Israel, accessed on October 23, 2026.
  14. 14The Jerusalem Post, Enlight launches largest solar-storage fusion project in Israel, accessed on October 23, 2026.
  15. 15The Jerusalem Post, Enlight brings renewable energy to Israel's border communities, accessed on October 23, 2026.
  16. 16CTech by Calcalist, Enlight launches two solar fields in Gaza envelope amid war, accessed on October 23, 2026.
  17. 17Globes, Enlight gets regulatory nod for Arava energy storage facility, accessed on October 23, 2026.
  18. 18The Times of Israel, accessed on October 23, 2026.
  19. 19Institute for National Security Studies, accessed on October 23, 2026.
  20. 20Globes, Enlight appoints sole female CEO of Tel Aviv 35 co, accessed on October 23, 2026.
  21. 21The Jerusalem Post, Enlight CEO: Iran war reinforces Israel's need for renewable energy, accessed on October 23, 2026.
  22. 22Globes, 3 Israeli cos sign renewable energy deals worth NIS 4.5b, accessed on October 23, 2026.
  23. 23Jewish News Syndicate, Netanyahu pauses Golan wind farm project for Druze holiday, accessed on October 23, 2026.
  24. 24The Times of Israel, accessed on October 23, 2026.

IsraelPedia Question & Answers

  • What is Enlight Renewable Energy?

    Enlight Renewable Energy is an Israeli company that develops, finances, builds, owns, and operates utility-scale solar, wind, and energy-storage projects. Founded in 2008, it grew from solar installations in Israel into an international business spanning Israel, Europe, and the United States. Its projects include Genesis Wind in the Golan Heights and facilities that combine solar generation with battery storage.

  • How does Enlight Renewable Energy earn revenue?

    Enlight Renewable Energy primarily earns revenue by selling electricity through long-term power-purchase agreements with electricity authorities, utilities, and corporations. Its Form 20-F describes typical agreement terms of 10 to 30 years. The company also sells some electricity in wholesale markets without a long-term contract or committed buyer, and uses short-term hedging to manage some exposure to those sales.

  • How did Enlight Renewable Energy expand internationally?

    Enlight Renewable Energy entered European solar markets in 2012 and European wind markets in 2014, then expanded into the Balkans in 2016 and Hungary’s solar market in 2017. In 2021, it entered the United States by acquiring a 90.1% equity interest in Clēnera, a utility-scale solar and storage developer focused particularly on the western United States. As of February 19, 2025, Enlight reported activity in 12 countries across three continents.

  • What is the Genesis Wind project?

    Genesis Wind is an Enlight Renewable Energy wind project in the Golan Heights with 39 turbines and 207 MW of installed capacity, including expansion. Its first turbine was commissioned in June 2023, and the project reached commercial operation in October 2023. The project included eight Golan Heights settlements and Aveeram Ltd. as partners, and its power was covered by an inflation-indexed agreement with Israel Electric Corporation through 2043.

  • What concerns have been raised about Enlight Renewable Energy’s wind projects?

    Enlight Renewable Energy’s Genesis Wind project faced opposition from Druze leaders and residents who said it encroached on their land; Enlight rejected claims that it had violated residents’ land rights. Wind development in the Golan Heights has also drawn environmental concerns, including potential ecological effects and risks to birds and bats. Enlight says it installed a radar-assisted system at Genesis to protect the Golan Heights vulture population; the cited reporting does not independently resolve the land-rights dispute.