01In brief
The Heletz railway is a freight railway line in southern Israel, built to shorten the route for transporting minerals from the Negev to Ashdod Port. Decided upon in November 1978 by the Ministry of Transport, Israel Railways, and several other government ministries and Israel Chemicals Ltd., the project combined 27 kilometers of rehabilitated coastal track with 21 kilometers of newly laid railway, for a total length of 48 kilometers. The completed line cut the distance between Kiryat Gat and Ashdod Port by 18 kilometers and saved nearly three hours per freight-train round trip by eliminating a stop at Lod station, a major bottleneck in the national rail network.
02Overview and Location
The Heletz railway runs through southern Israel, connecting Kiryat Gat to Ashkelon and linking into the coastal railway known as the Pleshet line.[1] It was conceived as part of the broader expansion of Israel Railways' southern network, alongside rail connections serving the phosphate and potash industries and the port of Ashdod.[1] The line's primary function is the movement of minerals from the south to Ashdod Port, serving the needs of Israel Chemicals Ltd. and the broader industrial freight sector.[1]
03Planning and Construction
In November 1978, the Ministry of Transport and Israel Railways, together with the Ministries of Finance and Industry and Trade and Israel Chemicals Ltd., formally decided to build the line from Kiryat Gat to Ashkelon.[1] Detailed planning began that same year, and to ensure momentum, Israel Railways' director general established a dedicated project administration in December 1978, headed by the director general himself and including representatives from the Finance and Transport ministries.[1] This body was tasked with resolving financial, staffing, and planning matters and with giving project-related work priority across railway units.[1]
Construction was completed in November 1982.[1] The project cost 267.7 million shekels at prices current on March 31, 1983, with Israel Railways issuing 24 tenders and signing 24 contractor agreements totaling approximately 80 million shekels.[1] Works encompassed two road bridges, one railway bridge, track and sleeper installation, earthworks, and construction of facilities at six stations: Kiryat Gat, Ashdod, Pleshet, Rehovot, Dvira, and Ashkelon.[1]
Approximately 1,000 dunams of agricultural land — some of it uncultivated — were expropriated for the project, with compensation totaling approximately 10 million shekels at March 1983 prices.[1] Possession of this land was taken only in May 1979, roughly six months after the formal expropriation order. The delay created significant disruption: landholders objected to the railway taking possession, and court intervention was ultimately required to resolve the disputes and allow construction to proceed.[1]
04Operational Benefits
The completed route shortened the distance between Kiryat Gat and Ashdod Port by 18 kilometers.[1] Crucially, it also eliminated the need for freight trains to stop at Lod station, which served as a bottleneck in the national railway system. Together, these improvements saved nearly three hours per freight-train round trip, a significant efficiency gain for the continuous movement of minerals to the port.[1]
Decades after its opening, the line continued to see infrastructure investment. In 2014, upgrading of the freight line in the Heletz area was completed, with that work reported among Israel Railways' broader infrastructure development activities for the year, alongside the promotion of new routes and the upgrading of older stations.[2] Systemwide, railway cargo totaled 7.5 million tons in 2014, up 12% from 6.7 million tons in 2013; those figures covered Israel Railways as a whole rather than the Heletz line.[2]
05State Comptroller Audit Findings
The State Comptroller's Office audited construction-related work between September and December 1983.[1] Its principal findings pointed to inadequate quantity estimates in some work specifications, cases of excess expenditure — particularly where prices paid for quantities performed exceeded the tender quantities — and departures from restricted-tender procedures.[1] The audit also identified insufficient materials testing. In eight of 24 examined concrete pours, no samples were submitted; among 12 cases in which samples were supplied, 10 had fewer samples than required by the specification.[1]
A separate dispute documented in the report concerned the terms for transporting minerals under the contract with Israel Chemicals Ltd. Israel Railways argued that the contract did not ensure its actual mineral-transport costs would be covered, while Israel Chemicals contended that a proposed 46% tariff increase exceeded what the railway was entitled to receive.[1] The Transport Ministry had promised to establish a committee to examine mineral-transport costs once the Heletz line entered service, but that committee had not been constituted by the time the audit concluded.[1]
Sources
- 1State Comptroller of Israel, Israel Railways report, accessed on September 26, 2026.
- 2Globes, Israel Railways passenger traffic up 7.5% in 2014, accessed on September 26, 2026.
IsraelPedia Question & Answers
What is the Heletz railway?
The Heletz railway is a freight railway line in southern Israel, built to shorten the route for transporting minerals from the Negev to Ashdod Port. The project combined 27 kilometers of rehabilitated coastal track with 21 kilometers of newly laid railway, for a total length of 48 kilometers. The decision to build it was made in November 1978 by the Ministry of Transport, Israel Railways, several other government ministries, and Israel Chemicals Ltd.
What route does the Heletz railway connect?
The Heletz railway runs through southern Israel, connecting Kiryat Gat to Ashkelon and linking into the coastal railway known as the Pleshet line. Its primary function is the movement of minerals from the south to Ashdod Port, serving the needs of Israel Chemicals Ltd. and the broader industrial freight sector.
When was the Heletz railway completed, and how much did it cost?
Construction of the Heletz railway was completed in November 1982. The project cost 267.7 million shekels at prices current on March 31, 1983, with Israel Railways issuing 24 tenders and signing 24 contractor agreements totaling approximately 80 million shekels.
What operational benefits did the Heletz railway provide?
The completed Heletz railway shortened the distance between Kiryat Gat and Ashdod Port by 18 kilometers and saved nearly three hours per freight-train round trip. These gains were achieved largely by eliminating the need for freight trains to stop at Lod station, which had served as a major bottleneck in the national railway network.
What problems arose during the construction of the Heletz railway?
Approximately 1,000 dunams of agricultural land were expropriated for the project, but possession was not taken until May 1979, roughly six months after the formal expropriation order. Landholders objected to the railway taking possession of their land, and court intervention was ultimately required to resolve the disputes and allow construction to proceed.
What did the State Comptroller's audit find about the Heletz railway project?
The State Comptroller's Office, auditing construction-related work between September and December 1983, found inadequate quantity estimates in some work specifications, cases of excess expenditure, and departures from restricted-tender procedures. The audit also identified insufficient materials testing: in eight of 24 examined concrete pours, no samples were submitted, and in 10 of the 12 cases where samples were supplied, fewer samples were provided than the specification required.