National Water Carrier of Israel

Published

01In brief

National Water Carrier of Israel is a water-conveyance system in Israel linking the Sea of Galilee and northern water resources with central and southern parts of the country. Its approximately 130-kilometer route combines pipelines, canals, tunnels, reservoirs, and pumping stations, and its construction employed more than 4,000 workers. Pumping began on June 10, 1964, supplying drinking water and agriculture while connecting most of Israel’s water systems. Initially oriented mainly toward agriculture, the carrier became increasingly important for urban supply and subsequently formed part of a national network incorporating groundwater and Mediterranean desalination plants. Its history connects the development of the Negev, large-scale Israeli engineering, and regional disputes over shared water resources.

02Overview and Location

The National Water Carrier connects the relatively water-rich north with central Israel and the arid south, making water available beyond the immediate surroundings of individual rivers, lakes, and wells.[6] Its north-to-south route helped make possible the establishment of towns in areas where difficult geographic conditions had previously constrained settlement.[2] Water carried through the system reaches coastal population centers, including Tel Aviv and Haifa, and extends southward toward the Negev Desert.[7]

The carrier is not simply a single pipe from the Sea of Galilee to the desert: its infrastructure includes open canals, underground pipelines, tunnels, pumping installations, and intermediate reservoirs.[1] Designed by Tahal and built and managed by the government-owned water company Mekorot, it brought previously separate resources into a more closely connected supply system.[8] Most of Israel’s water systems were integrated with the carrier, whose maximum conveyance rate has been given as 1.7 million cubic meters per day.[1]

The Sea of Galilee, also called Lake Kinneret, was the northern starting point of the original conveyance scheme.[6] Together with the Mountain and Coastal aquifers, it became part of a connected national supply system serving agricultural and urban consumers.[6] Linking these sources increased operational flexibility and allowed water to be shifted between regional systems as availability and demand changed.[6][6]

The broader national network extends from the Sea of Galilee to Mitzpe Ramon, rather than supplying every part of Israel through the same north-to-south arrangement.[3] Areas farther south, including the Arava Valley and Eilat, rely on local brackish groundwater and desalinated water.[3] The carrier’s place within this network has changed as desalination and treated-water recycling have become more important in responding to water scarcity.[9]

03History

Plans to convey water to the Negev were being developed from 1939 onward, chiefly through the work of engineer Simcha Blass.[6] These proposals addressed the possibility of supporting a larger population and developing the south by transferring water from other regions.[2] Blass’s staged approach began with nearby wells and progressed toward bringing water from the Yarkon and northern rivers.[10] Levi Eshkol also participated in the planning of large-scale water projects.[6]

Mekorot prepared a comprehensive study of water resources in 1944, while American specialists including Walter C. Lowdermilk and James B. Hays examined development possibilities.[6] Lowdermilk’s 1944 book, The Land of Israel, the Promised Land, advanced one proposal for using northern water in the development of the south.[2] Jewish Agency leaders subsequently asked Hays to devise a scheme involving the Yarmouk, Jordan, and Litani rivers for the Negev.[2] These proposals were also used to argue that a future Jewish state could absorb substantial immigration.[2]

The carrier followed earlier projects that had already established the principle of carrying water over long distances to the arid south.[6] A Negev pipeline installed in 1947 initially consisted of 190 kilometers of six-inch pipe and supplied one million cubic meters annually.[6] It was later converted to a 20-inch pipeline carrying 30 million cubic meters a year.[6] The subsequent Yarkon–Negev pipeline conveyed 100 million cubic meters annually over a distance of 130 kilometers, but a larger and more comprehensive system was soon considered necessary.[6]

David Ben-Gurion decided in 1951 to proceed with a national carrier, linking the project to the development of a technologically advanced society and the dispersal of population across the country, including the Negev.[2] Initial planning was undertaken by the Agriculture Ministry’s Water Department under Blass; from 1952, responsibility passed to Tahal, the Israel Water Planning company that Blass had also established.[10] Hays later worked with J. S. Cotton, whose 1955 master plan was adopted by the government as the blueprint for planning and constructing the carrier.[6]

Preliminary project work began in 1953, before the approval of Tahal’s design in 1956 and the main construction period under Mekorot.[1] The original scheme proposed drawing water from the Jordan River before it entered Lake Kinneret, but the design was subsequently changed to take water from the lake itself.[6] In February 1956, the national water-project planning committee and an advisory council of international water experts approved the plan, and execution was transferred to Mekorot that year.[10] Mekorot began the main construction phase in 1959, with work continuing for five years.[1]

The project required more than 4,000 workers and approximately 2.5 million workdays.[10] Construction involved excavating seven million cubic meters of earth, quarrying about 1.7 million cubic meters of rock, casting roughly 500,000 cubic meters of concrete, and laying 15,000 concrete and steel pipes.[10] Its reported cost was 420 million Israeli pounds, also described as Israeli lira.[2][10] Three tunnels were built to carry water through hills along the route.[11]

Pumping from the Kinneret began on June 10, 1964, supplying drinking water and agriculture in central and southern Israel.[1] The inauguration was deliberately low-key and kept secret until shortly beforehand, reflecting concerns about neighboring states, sabotage, contamination, and domestic criticism over allocation and operating arrangements.[10] Prime Minister Levi Eshkol chose a small, private ceremony rather than a large public celebration because of concern that it could provoke a Syrian attack.[12]

At the beginning of operations, agriculture received approximately 80 percent of the water and drinking-water supply about 20 percent.[3] The agricultural share reflected the project’s early orientation toward irrigation, while population growth subsequently increased the importance of household supply.[1] By the beginning of the 1990s, the carrier supplied about half of Israel’s drinking water.[10]

04Route and Engineering

Water entering the original carrier from Lake Kinneret must first be lifted out of a basin lying below sea level before it can continue toward the coastal region and the Negev.[6] The overall conveyance scheme raises lake water from approximately 220 meters below sea level to an elevation of about 152 meters above sea level, after which it flows by gravity toward the coast and is pumped onward to the south.[6] This combination of pumping and gravity flow is implemented through a succession of canals, reservoirs, tunnels, and pipelines rather than a single continuous lift.[6]

At the Sapir site near the Kinneret, three large pumping units raise water from approximately 213 meters below sea level to 44 meters above sea level.[13] A fourth unit was inaugurated in 1991 to provide backup capacity.[13] The units were installed inside a nearby mountain, a location that also offered protection from Syrian positions on the Golan Heights.[13] The first stage therefore combines the practical requirement of lifting lake water with the protected placement of major pumping machinery.[13]

The route crosses the Nahal Amud valley through a siphon system based on communicating vessels, allowing water to pass between high banks without an additional pumping station at the crossing.[13] It then travels through the 17-kilometer Jordan Canal to the Tzalmon reservoir.[13] After another siphon at Nahal Tzalmon, water is raised to 152 meters above sea level and continues through the 17-kilometer Netofa Canal toward the Eshkol reservoir in the Beit Netofa Valley.[13]

At Eshkol, water undergoes settling, biological treatment, disinfection, and additional filtration before entering the main pipeline.[13] One description gives an example of turbidity falling from a value of five to one during treatment and identifies the outlet pipe as three meters in diameter.[13] From there, water travels approximately 87 kilometers underground through tunnels and hills to the Yechiel station at Rosh HaAyin, where major lines direct it toward the south and the Tel Aviv metropolitan area.[13] A separate engineering description identifies a 77-kilometer concrete main-pipeline section leading to Rosh HaAyin.[11]

The carrier’s engineering capacities have been expressed in several different ways, including maximum daily conveyance, annual pumping capacity, and estimated annual transport.[1][3] A 1962 engineering assessment estimated that the conduit could carry between 400 million and 550 million cubic meters a year.[14] The combined stated capacity of its three pumps was 615 million cubic meters, although the assessment assumed that normally only two pumps would operate simultaneously.[14] These figures concern different components and operating assumptions, rather than one uniform measure of annual delivery.[14]

A later account describes annual transport of approximately 400 million cubic meters, while the national water-sector research report gives approximately the same figure for the annual pumping capacity from the Sea of Galilee into the carrier.[8][3] Actual pumping from the lake was considerably lower in the years preceding that report.[3] The distinction between installed capacity and actual pumping became increasingly important as the national system gained additional sources, particularly coastal desalination plants.[3]

05Water Management and Treatment

The connected delivery system was designed to bridge three recurring mismatches: water-rich and water-scarce regions, winter rainfall and summer consumption, and wet and dry years.[6] By linking sources rather than relying only on isolated local supplies, the carrier allows water to be shifted as conditions and demand change.[6] Its reservoirs and interconnections therefore serve a wider management function than straightforward north-to-south transportation.[6]

The carrier draws on groundwater as well as surface water, integrating the Mountain and Coastal aquifers with the Kinneret.[6] A historical technical account gives annual aquifer contributions of about 350 million cubic meters from the Mountain Aquifer and 250 million from the Coastal Aquifer.[6] These figures describe contributions within the connected system, alongside the separate figures given for conveyance from the lake.[6] Water from additional underground sources, reservoirs, and desalination also enters the network along its course.[13]

The system can carry northern surplus water during winter and early spring and use it to recharge underground aquifers in the coastal region.[6] Water not immediately required by consumers can be directed into spreading basins and dual-purpose wells for recharge.[15] One account describes the interconnected supply network as serving about 1,000 major consumers, including 18 municipalities and 80 local authorities.[15] The same arrangement supplies a blend of surface water and groundwater rather than necessarily delivering water from one source to every consumer.[15]

Groundwater management also requires attention to salinity, particularly near the coast, where pumping can cause saline water to enter groundwater reserves.[9] Reducing reliance on these reserves, and treating them as an emergency resource, forms part of the rationale for desalination and treated-water recycling.[9] In the broader central supply system, the amounts taken from the Kinneret, its surroundings, the Coastal and Mountain aquifers, and desalination plants can be regulated through their integration into a common network.[3]

The carrier was initially designed principally for agriculture, and much of its water passed through open canals or pipes without filtration.[11] After its transfer to Mekorot, the water was designated for drinking and subjected to regular quality inspections.[11] The increasing importance of household supply consequently placed greater emphasis on treatment as well as conveyance.[11]

Mekorot’s Central Filtration Plant at Eshkol filters Kinneret water transported through the carrier and has an annual capacity exceeding 500 million cubic meters.[8] The plant complements the settling, biological treatment, disinfection, and additional filtration processes associated with the Eshkol reservoir and the main pipeline’s intake.[13]

06Development, Agriculture, and Urban Supply

The carrier made northern water available for settlement and agriculture in the Negev, extending the approach established by the earlier Negev and Yarkon–Negev pipelines.[6] Its planning was closely connected with the early state’s efforts to accommodate immigration, develop agriculture, and encourage settlement in the south.[4] Before its completion in June 1964, the water sector relied on local water enterprises and used approximately 800 million cubic meters annually.[4]

The establishment of a main national water line helped overcome geographic constraints on the placement of towns.[2] Ben-Gurion’s decision to proceed linked water infrastructure to population dispersal and the aspiration to build a modern society using advanced technology.[2] The project thus connected the practical supply of irrigation and drinking water with a broader program of national development extending beyond existing population concentrations.[2]

The original allocation of four-fifths of the carrier’s water to agriculture did not remain the governing pattern of demand.[1] Population growth and changing consumption habits increased urban requirements and pressure on freshwater resources.[3] The carrier alone could not meet both agricultural and household demand, making additional supplies and other water-management measures necessary.[16] Desalination and recycled treated water subsequently became important elements of Israel’s response to scarcity.[9]

The extension of the network also affected communities beyond its principal coastal and southern route.[17] In the late 1970s and 1980s, long pipelines connected new Israeli settlements in the West Bank — known by its original, indigenous Jewish name of Judea and Samaria — to the carrier along the coastal plain.[17] Palestinian villages and towns situated along those pipelines were also connected to running water.[17]

Water diversion also had environmental consequences within the wider history of north-to-south supply.[18] Beginning in 1955, diversion of Yarkon water through pipelines for irrigation in the Negev contributed to the river’s deterioration.[18] As sewage replaced freshwater flows, habitats were destroyed and flora and fauna disappeared.[18] This environmental history accompanied the expansion of water delivery to consumers outside the source river’s immediate basin.[18]

07Desalination and Reverse Conveyance

The expansion of seawater desalination changed the intended geography of national water supply: Kinneret water would increasingly be used near the lake, while water from the coast and natural groundwater sources would move across the country.[19] This differed from the original emphasis on carrying northern freshwater toward central and southern consumers.[6][19] The national system consequently developed around a more varied set of sources rather than depending on the original lake-to-south flow alone.[3]

A separate development described as the “new National Water Carrier” consists of 100-inch pipelines in central Israel designed to receive water from Mediterranean desalination plants and distribute it throughout the country.[20] Mekorot developed this infrastructure as desalination capacity expanded.[20] Its function reflects the growing importance of coastal production within the integrated national network.[20]

The Reverse Water Carrier, launched in December 2022, allows desalinated Mediterranean water to move inland toward the Kinneret, reversing the original supply concept.[21] The NIS 1 billion project was intended to help preserve lake levels during dry years, while maintaining the Kinneret’s ecological importance and its role as an emergency reserve.[21] It was designed to return as much as 120 million cubic meters annually.[21]

The first stage included a 30-kilometer pipeline from the Eshkol pumping station near Nahal Zalmon.[21] A later stage involved four pumping stations and ponds in the Rosh HaAyin area.[21] These works were conceived in response to a series of drought years during which the Kinneret’s level declined consistently from 2013 to 2018.[21]

During that decline, the lake reached the “black line” at 213 meters below sea level, the level at which pumping for the economy was halted.[21] By the December 2022 launch, several wet winters had raised the lake, and there was no immediate operational need for the new system.[21] The project nevertheless provided the means to supplement the lake in future dry conditions, even as desalination supplied much of Israel’s household water.[21]

08Regional Water Disputes

Work on the original intake began at Gesher B’not Ya’akov in July 1953, north of the Sea of Galilee and within a demilitarized zone.[5] Syrian protests and firing on construction and engineering sites were followed by the relocation of the intake to Eshed Kinrot on the lake’s northwestern shore.[5] Israel also suspended work after the United Nations ordered a halt while reviewing Syria’s complaint; the more expensive lake-based alternative avoided the armistice-zone issue.[22]

The Johnston negotiations of 1953–1955 produced a proposed Unified Plan allocating 400 million cubic meters annually to Israel, 720 million to Jordan, 132 million to Syria, and 35 million to Lebanon.[5] The plan was not ratified, although its technical details and allocations generally guided subsequent unilateral development; Palestinians received no explicit allocation as a separate negotiating entity.[5] The allocations were not legally binding but also served as a guide for American support of Israeli and Jordanian projects.[14]

After the carrier became operational, Arab states pursued a headwater-diversion scheme, with construction beginning in 1965, that would direct the Hasbani toward the Litani and the Banias toward the Yarmouk.[5] Israeli forces attacked diversion works in Syria in 1965.[5] The carrier’s early operation was therefore embedded in a wider conflict over shared waters and competing claims to their use.[5]

Domestic disputes included a rejected 1962 appeal by residents of Sakhnin and Arraba against the expropriation of 1,200 dunams in the Beit Netofa Valley, disagreements among agricultural groups over allocation, and objections by orchard owners to chloride levels.[10] Shortly before inauguration, residents of Galilee towns including Nazareth and Shafaram also protested out of concern that connection to the national grid could erode their national identity.[12]

Sources

  1. 1Center for Israel Education, National Water Carrier Begins Pumping, accessed on November 28, 2026.
  2. 2Central Zionist Archives, The National Water Carrier, accessed on November 28, 2026.
  3. 3The Knesset, Knesset Research and Information Center, “Israel’s Water Sector—Key Issues, accessed on November 28, 2026.
  4. 4The Knesset, The Parliamentary Committee of Inquiry on the Israeli Water Sector, accessed on November 28, 2026.
  5. 5United Nations Digital Library, Hydropolitics along the Jordan River, accessed on November 28, 2026.
  6. 6Jewish Virtual Library, Historical & Technological Aspects in Development of Limited Water Resources, accessed on November 28, 2026.
  7. 7Begin-Sadat Center for Strategic Studies, Water and Israeli National Security, accessed on November 28, 2026.
  8. 8Jewish Virtual Library, Water in Israel: Innovations Help Water a Thirsty Planet, accessed on November 28, 2026.
  9. 9Institute for National Security Studies, Special for Shavuot: Why is Israel no longer dehydrated?, accessed on November 28, 2026.
  10. 10Ynet, Syrian Mines and Nasser’s Threats: The Jewish State’s “Life-Giving Project”, accessed on November 28, 2026.
  11. 11Globes, 10 Things About the National Water Carrier, accessed on November 28, 2026.
  12. 12Ynetnews, 50 years later, National Water Carrier still an inspiration, accessed on November 28, 2026.
  13. 13Ynet, The National Water Carrier: A Tour Inside Israel’s Aorta, accessed on November 28, 2026.
  14. 14Office of the Historian, Historical Documents, accessed on November 28, 2026.
  15. 15Jewish Virtual Library, Water in Israel: Israel's Chronic Water Problem, accessed on November 28, 2026.
  16. 16Jewish Virtual Library, How Israel Used Innovation To Beat Its Water Crisis, accessed on November 28, 2026.
  17. 17Begin-Sadat Center for Strategic Studies, Water Infrastructure, accessed on November 28, 2026.
  18. 18Jewish Virtual Library, Water in Israel: Rehabilitation of Israel's Rivers, accessed on November 28, 2026.
  19. 19OECD, Environmental Performance Reviews: Israel 2011, accessed on November 28, 2026.
  20. 20Globes, Desalination plants ensure water supply until 2025, accessed on November 28, 2026.
  21. 21Globes, Reverse water carrier launched to refill Kinneret, accessed on November 28, 2026.
  22. 22Center for Israel Education, Israel Begins Jordan River Project, accessed on November 28, 2026.

IsraelPedia Question & Answers

  • What is the National Water Carrier of Israel?

    The National Water Carrier of Israel is a water-conveyance system that links the Sea of Galilee and northern water resources with central and southern Israel. Its approximately 130-kilometer route combines pipelines, canals, tunnels, reservoirs, and pumping stations. The system supplies water for drinking and agriculture and connects most of Israel’s water systems.

  • When did the National Water Carrier begin operating, and what was it initially used for?

    Pumping from the Kinneret began on June 10, 1964, supplying drinking water and agriculture in central and southern Israel. At the beginning of operations, agriculture received approximately 80 percent of the water and drinking-water supply about 20 percent. By the beginning of the 1990s, the carrier supplied about half of Israel’s drinking water.

  • How does water travel through the National Water Carrier?

    Water from Lake Kinneret is lifted from below sea level and then moves through a sequence of canals, reservoirs, tunnels, and pipelines toward central and southern Israel. At Eshkol, it undergoes settling, biological treatment, disinfection, and additional filtration before entering the main pipeline. The route uses both pumping and gravity flow.

  • How did desalination change the National Water Carrier’s role?

    As seawater desalination expanded, the national network began moving water from the coast and natural groundwater sources across the country, while Kinneret water could increasingly be used near the lake. The Reverse Water Carrier, launched in December 2022, allows desalinated Mediterranean water to flow inland toward the Kinneret. It was designed to return as much as 120 million cubic meters annually and help preserve lake levels during dry years.

  • Why did construction of the National Water Carrier become a regional dispute?

    The original intake work began at Gesher B’not Ya’akov in July 1953, north of the Sea of Galilee and within a demilitarized zone. Syrian protests and firing on construction and engineering sites led to the intake being relocated to Eshed Kinrot on the lake’s northwestern shore. The carrier also became part of wider disputes over shared waters, including Arab states’ headwater-diversion scheme, whose construction began in 1965.

  • What environmental impact accompanied the expansion of water delivery?

    Beginning in 1955, diversion of Yarkon water through pipelines for Negev irrigation contributed to the river’s deterioration. As sewage replaced freshwater flows, habitats were destroyed and flora and fauna disappeared.