Highway 50 (Israel–Palestine)

Published

01In brief

Highway 50 is a north–south expressway in Jerusalem, also known as the Begin Highway, Begin Expressway, or Begin Boulevard. Its development formed part of Jerusalem’s broader post-1967 road-building program. The 16-kilometer route connects the Ramot area with Gilo and provides onward connections toward Gush Etzion; its southern extension through Beit Safafa prompted resident protests and litigation. A plan approved in 2025 envisages covering a central stretch with a new urban development incorporating housing, public facilities, and commercial space.

02Overview and Location

Highway 50 runs approximately 16 kilometers from near Ramot in northern Jerusalem, where it continues from Route 443, to Gilo in the south.[1] At its southern end, the route connects with Route 60 and the Tunnels Highway toward Gush Etzion.[1] The expressway is a principal north–south traffic artery through Jerusalem, linking northern and southern parts of the city without requiring traffic to follow its older central streets.[1][3]

The road has ten bridges and two tunnels.[1] A 2017 description of the completed route gave a normal-traffic journey time of about 12 minutes from one end to the other, without traffic lights.[6] When the southern section opened in April 2016, however, the connection to the Tunnels Highway still had traffic lights, pending construction of an interchange.[1] The Rosmarin Interchange in Gilo was subsequently identified as the project that would complete the highway’s connection to Route 60 and the Tunnels Highway.[6]

03History

Jerusalem’s post-1967 transport planning sought alternatives to existing thoroughfares, especially Jaffa Road, which were inadequate for both urban and interurban traffic.[3] Broad new routes were intended to allow vehicles to cross the municipal area toward destinations beyond it—for example, “from Bethlehem directly to Ramallah”—without adding to congestion on the main arteries.[3] Roads between the formerly separated parts of Jerusalem were joined and opened as part of the city’s post-1967 transport expansion.[3]

The city’s hilly terrain and protected historic sites made road construction expensive, requiring extensive earth-moving, demolitions, and long tunnels.[3] Begin Boulevard became the main north–south artery, with a tunnel beneath the western entrance to the city and connections to the access-road system associated with Route 443.[3] Other projects included tunnels toward the Etzion Bloc, a Mount Scopus tunnel toward Ma’aleh Adumim, and a bridge road connecting Pisgat Ze’ev and Neveh Ya’acov with the French Hill junction.[3] In 2006, Route 9 was under construction in Emek ha-Arazim to connect the Motza and Ramot junctions with Begin Boulevard near Mount Hotzvim.[3]

The Begin Highway opened to traffic in 1998.[7] Its first section linked Ramot with Malha through a tunnel beneath Jerusalem’s western entrance.[6] During planning, a burial cave was discovered in the path of a proposed lane; following pressure from Knesset member Meir Porush of Agudat Yisrael, the cave was preserved rather than the lane.[7] In 2010, widening proceeded on the opposite side through excavation of the Givat Ram slope, at a reported cost of NIS 2 million, instead of relocating the cave.[7] A 2022 account stated that the cave’s large stone remained in the middle of the road.[7]

A separate element of the regional network was Highway 22, described in a 2004 transport study as continuing from the Begin North freeway toward Hizma and Jericho.[8] At that time, Highway 22 was expected to take priority and temporarily replace Highway 45, which had been truncated by the separation barrier.[8]

04Southern Extension

The southern extension appeared in a master plan dating to the late 1960s and had officially been in development since 1990.[9] Its route was originally intended to follow Beit Safafa’s southern edge, but the neighborhood’s growth placed the planned alignment through its center.[9] The route was the subject of neighborhood protests by March 2013.[10]

The project included a 1.8-kilometer connection through Beit Safafa between the Begin Highway and the Tunnel Road leading toward Gush Etzion.[4] It was intended to ease traffic to and from Gilo and improve access to Jerusalem for residents of the Etzion Bloc settlements in the West Bank — known by its original, indigenous Jewish name of Judea and Samaria.[9] The state presented the extension as a means of improving travel within Jerusalem and producing economic benefits.[4]

Construction of Begin South from Malha to Gilo took six years and cost NIS 1.5 billion.[6] The southern section linking Gilo with the Gush Etzion tunnels highway opened on April 20, 2016.[1] It included a 180-meter tunnel beneath Beit Safafa, while the junction with the Tunnels Highway initially retained traffic lights.[1] In September 2017, the Rosmarin Interchange was presented as the final connection needed to complete the highway.[6]

05Highway Cover and Urban Development

In October 2020, Jerusalem’s Local Planning and Building Committee approved a proposal to cover a 1.6-kilometer stretch of Begin Boulevard between the Hebrew University’s Givat Ram campus and Beit Hakerem.[2] The proposal envisaged a park, walking and cycling routes, housing, sheltered housing, hotel rooms, commercial and office space, and public buildings.[2] Its estimated cost was NIS 1.2 billion, and it was promoted by the Israel Land Authority, Jerusalem Municipality, and Jerusalem Development Authority.[2]

The Jerusalem District Planning and Building Committee approved the highway-cover plan in July 2025.[5] The approved area comprised 215 dunams along a 1,600-meter stretch between the Beyt Interchange and Wolfson Bridge.[5] It envisaged approximately 2,000 housing units, 250 assisted-living units, 300 hotel rooms, 30,000 square meters of office and commercial space, and 75,000 square meters for public use.[5]

Planned buildings ranged from six to fifteen floors, with towers reaching as high as 45 floors.[5] An agreement between Jerusalem Municipality and the Israel Land Authority provided for a dedicated administration to implement the project.[5] The project was described at approval as Israel’s first road-roofing scheme on this scale.[5]

06Planning Disputes

Beit Safafa residents opposed the southern extension because it passed through the middle of their neighborhood.[4] The neighborhood had been divided under the 1949 armistice arrangements, with its northern part inside Israel, and its two parts were reunited after the 1967 war.[11] Major roads, including Route 50, subsequently divided it into four parts.[11] On March 1, 2013, approximately 300 residents demonstrated against the construction and attempted to block nearby Dov Yosef Road; police dispersed them and arrested one person.[10]

Residents and community advocates argued that the highway would divide the neighborhood, damage quality of life, and primarily benefit traffic to Gush Etzion rather than local residents.[9] Their objections included fears of pollution and restrictions on nearby building, while a construction-site slogan read, “Don’t run over Beit Safafa.”[12][9] Advocates alleged that residents lacked an opportunity to object to a detailed plan; the municipality rejected that claim, citing opportunities for participation during the plan’s 23-year zoning process and emphasizing the project’s citywide economic value.[9]

In January 2014, the Supreme Court upheld the state’s right to build the road but canceled certain access roads and required an updated master plan before work proceeded.[4] The state had committed to providing alternatives before removing streets or walkways, so that no part of the neighborhood would be cut off during construction.[4] Residents sought additional overpasses and longer protective walls where the highway would pass within three meters or less of some homes; the state agreed to 180 meters of walls and some overpasses but argued that further demands were physically impracticable and could cost more than NIS 100 million.[4]

The highway-cover project also attracted objections, including opposition to high-rise construction and its possible effects on Beit Hakerem.[2] By December 2024, 685 objections had been filed, mostly by residents.[13] Institutional objections concerned contaminated land near the Beit Hakerem industrial and commercial zone, potential harm to the Israel Geological Institute’s activities, and effects on the Hebrew University technology park; Jerusalem Municipality also submitted an objection despite being a project developer.[13]

Sources

  1. 1Globes, Southern section of Jerusalem highway opens, accessed on November 12, 2026.
  2. 2Globes, Jerusalem approves Begin Highway cover and park, accessed on November 12, 2026.
  3. 3Encyclopedia.com, Jerusalem, accessed on November 12, 2026.
  4. 4The Jerusalem Post, Supreme Court upholds controversial Jerusalem road, with modifications, accessed on November 12, 2026.
  5. 5Globes, Jerusalem District C'ttee approves plan to cover Begin Highway, accessed on November 12, 2026.
  6. 6Globes, New interchange completes Jerusalem's Begin Highway, accessed on November 12, 2026.
  7. 7Calcalist, From protests against the train to roads specially for Shabbat: Jerusalem’s transportation ordeal, accessed on November 12, 2026.
  8. 8Jerusalem Institute for Policy Research, A Fence Around Jerusalem, accessed on November 12, 2026.
  9. 9The Times of Israel, New Expressway Inflames Jerusalem Neighborhood, accessed on November 12, 2026.
  10. 10Ynet, Jerusalem: Hundreds of Beit Safafa residents protested road paving; one demonstrator arrested, accessed on November 12, 2026.
  11. 11Globes, Beit Safafa neighborhood in the heart of Jerusalem: The neighborhood frozen together, accessed on November 12, 2026.
  12. 12The Jerusalem Post, Beit Safafa residents angry over highway set to divide village, accessed on November 12, 2026.
  13. 13Globes, 700 objections on plan to cover Jerusalem's Begin Highway, accessed on November 12, 2026.

IsraelPedia Question & Answers

  • What is Highway 50 in Jerusalem?

    Highway 50 is a north–south expressway in Jerusalem, also known as the Begin Highway, Begin Expressway, or Begin Boulevard. The approximately 16-kilometer route runs from near Ramot in the north to Gilo in the south, connecting with routes toward Gush Etzion. It is a principal traffic artery linking the northern and southern parts of the city.

  • Why was Highway 50 built?

    Highway 50 was part of Jerusalem’s post-1967 transport expansion, which sought alternatives to existing thoroughfares such as Jaffa Road. New routes were intended to let traffic cross the city toward destinations beyond it without adding to congestion on its main arteries. The Begin Highway opened to traffic in 1998.

  • When did the southern section of Highway 50 open?

    The southern section of Highway 50, linking Gilo with the Gush Etzion tunnels highway, opened on April 20, 2016. The section included a 180-meter tunnel beneath Beit Safafa. The junction with the Tunnels Highway initially retained traffic lights, and the Rosmarin Interchange was later identified as the connection needed to complete the route.

  • Why did Beit Safafa residents protest the Highway 50 extension?

    Beit Safafa residents opposed the extension because its route passed through the middle of their neighborhood, dividing it and, they argued, damaging quality of life. Residents and community advocates also raised concerns about pollution, limits on nearby building, and whether the road would mainly benefit traffic to Gush Etzion rather than local residents. In January 2014, the Supreme Court upheld the state’s right to build the road but canceled certain access roads and required an updated master plan before work proceeded.

  • What is planned for the Highway 50 cover project?

    The Highway 50 cover plan, approved by the Jerusalem District Planning and Building Committee in July 2025, would cover a 1,600-meter stretch between the Beyt Interchange and Wolfson Bridge. It envisages approximately 2,000 housing units, 250 assisted-living units, 300 hotel rooms, 30,000 square meters of office and commercial space, and 75,000 square meters for public use. Planned buildings range from six to fifteen floors, with towers reaching as high as 45 floors.

  • What objections were raised to the Highway 50 cover plan?

    Objections to the Highway 50 cover plan included opposition to high-rise construction and concerns about possible effects on Beit Hakerem. By December 2024, 685 objections had been filed, mostly by residents. Institutional objections raised concerns about contaminated land, potential harm to the Israel Geological Institute’s activities, and effects on the Hebrew University technology park; Jerusalem Municipality also submitted an objection despite being a project developer.