01In brief
Highway 22, also known as the Krayot Bypass, is a highway in the Krayot area near Haifa in northern Israel. Its development included a planning condition that could have prevented the completed road from opening until nearby liquefied petroleum gas storage tanks were buried. The 14-kilometer highway opened fully in 2013 and was built to ease congestion in Haifa Bay.
02Overview
The Krayot Bypass was planned as a signal-free alternative to the congested Histadrut Boulevard section of Highway 4 between Acre and Haifa’s Check Post junction.[3] Its regional connections include Highway 4, the Carmel Tunnels, Haifa’s Lower City, the Krayot, Acre, Nahariya, and communities in the Western Galilee.[4]
The completed route was described in March 2013 as extending 14 kilometers from Independence Street in Haifa to Kibbutz Ein HaMifratz, linking Haifa’s Lower City with the southern approaches to Acre.[5] A 2009 project description listed five planned interchanges: Histadrut Boulevard, Kiryat Ata South, Kiryat Ata North, Kiryat Bialik, and Karei Ne’eman.[3] A 2018 description presented the road as a 14-kilometer, signal-free route with five interchanges, three lanes in each direction, and a reported speed of 110 km/h.[4]
03History
The bypass alignment was moved east during the 1970s and 1980s following public opposition to an earlier route, and Yefe Nof planned the revised alignment during the 1990s and early 2000s.[6] At a 2007 Knesset committee hearing, Kiryat Bialik mayor Rafi Wertheim outlined a roughly 12-kilometer route from Vulcan Junction to the northern Karei Ne’eman area.[6] His account of the 2002–2003 statutory plan described two lanes in each direction and a suburban or intercity railway in the center, within a 50-meter-wide corridor.[6] He also described changes to the plan in 2005 and five planned interchanges in Kiryat Bialik in addition to Vulcan Junction; these were planning proposals rather than a description of the completed highway.[6]
Financing was initially envisaged through a toll-road, public-private BOT arrangement.[3] During a 2007 hearing, the Finance Ministry estimated the project’s cost at about NIS 2 billion and presented tolls as a means both of financing construction and managing traffic.[7] Its representative warned that a budget-funded alternative might not be built within the following five years, while stating that NIS 400 million in state funding would be invested in either case.[7] Local representatives opposed tolls, raising concerns about access and the diversion of traffic onto neighborhood roads, and the committee chair called for Krayot residents not to be charged.[7]
The project ultimately proceeded as a contractor-led scheme financed from the state budget as part of an economic stimulus program.[3] In 2009, its estimated overall cost was about NIS 1.9 billion, including approximately NIS 1.2 billion in contracted works and the remainder for land acquisition, compensation, and maintenance.[3] During construction, H.P.T. managed the works for the National Roads Company, with Shapir as the main contractor.[8]
Planning objections concerned the road’s proximity to homes, environmental review, and noise protection.[6] At the 2007 hearing, a resident questioned whether environmental assessments had been prepared; a planning official said the approved plan included environmental and acoustic assessments, while an environmental planner said a detailed acoustic appendix had not yet been received.[6] Project representatives said noise-protection measures formed part of the design.[6]
Nearby LPG storage facilities also affected preparations for opening the highway.[2] A planning condition barred opening until the tanks had been buried, prompting concern that the publicly funded road could be physically complete but unavailable for use.[2] A September 2012 account of the first major opening reported that the High Court of Justice had rejected a petition by three gas companies operating the northern gas farm and required them to bury or relocate the facility.[8]
The first major opening involved an eight-kilometer section between Yadin Interchange and Bialik Interchange, scheduled for September 2012, about six months ahead of plan.[8] This section included the Histadrut, Kiryat Ata South, Kiryat Ata North, and Bialik interchanges, with a reported speed limit of 100 km/h.[8] The construction-stage description specified two carriageways with two lanes each, lighting along the route, and acoustic walls separating it from neighboring areas.[8]
By March 2013, the main section from the Technical School area to Kiryat Bialik had opened the previous September, and the final section was due to open in both directions.[5] The road’s completion followed nearly 20 years of preparations and disputes with local authorities along the route.[5] The highway opened fully in 2013.[1]
An earlier opening had produced a bottleneck at the connection to Road 79, where peak-period journeys from the exit to Highway 4 sometimes took half an hour or more.[5] Final works included widening part of Highway 4 to six lanes, constructing service roads, and adding two pedestrian bridges.[5] One bridge was near Kfar Masaryk; the other connected the Ein HaMifratz shopping center with southern Acre’s industrial area.[5]
In March 2014, Yefe Nof opened a roughly 1.7-kilometer connection between the Carmel Tunnels and the Krayot Bypass, enabling continuous travel from southern Haifa to Karei Ne’eman near Acre without using Histadrut Boulevard.[9] Construction had begun in summer 2011 and cost NIS 260 million.[9] The link comprised a dual-carriageway road with two lanes, including about 600 meters lowered beneath the Coastal Railway, the Valley Railway, and the Metronit route.[9]
A subsequent infrastructure program listed the Highway 22 Chen–Kiryat Bialik Interchange as under implementation, with an estimated construction cost of NIS 122 million.[10] The project involved an interchange over the existing bypass, together with stream-regulation and drainage works, and was listed in Haifa.[10]
04Economy and Transport
The highway was intended to relieve heavy traffic on Histadrut Boulevard while serving the Krayot and communities farther north.[6] A construction-stage estimate anticipated a journey of about 15 minutes between Acre and Haifa’s outskirts, compared with 40–50 minutes through the Krayot; this was an expected benefit rather than a measured post-opening journey time.[8] By 2018, the road was described as having substantially reduced congestion in the Haifa–Krayot metropolitan area and as a prototype for the Transport Ministry’s design-build project delivery approach.[4]
Published expenditure figures reflected different stages and scopes of the project: the investment was put at NIS 1.7 billion in 2012, while the March 2013 account distinguished approximately NIS 1 billion for paving, construction, and interchanges from a total cost of about NIS 2 billion.[8][5] A later account placed the project budget above NIS 1.6 billion.[1]
For the Carmel Tunnels connection, Yefe Nof projected a 15–25 percent increase in traffic volumes and approximately NIS 100 million in economic savings during its first year.[9] The forecast included daily reductions of 621 vehicle-hours and nearly 4,930 vehicle-kilometers; these figures were projections, not recorded outcomes.[9]
In 2017, no buses operated on Highway 22.[1] The Transport Ministry explained this arrangement by pointing to the Metronit service on Highway 4, which operated as a collector service with an exclusive right-of-way.[1]
Sources
- 1Ynet, New roads worth billions, without public transport: “The message to the public is—you need a car”, accessed on November 19, 2026.
- 2The Knesset, Committee Protocol on LPG Storage and the Krayot Bypass, accessed on November 19, 2026.
- 3Globes, Solel Boneh, Ashtrom, Shapir Engineering and Danya Cebus to submit bids next week for the Krayot Bypass, accessed on November 19, 2026.
- 4Ynet, The National League, accessed on November 19, 2026.
- 5Ynet, The Krayot Bypass is complete—we drove on it for the first time, accessed on November 19, 2026.
- 6The Knesset, Interior and Environmental Protection Committee, Protocol 213, accessed on November 19, 2026.
- 7The Knesset, Economic Affairs Committee, Protocol 398, accessed on November 19, 2026.
- 8TheMarker, The Krayot Bypass: From Haifa to Acre in ten minutes, accessed on November 19, 2026.
- 9Calcalist, Six months ahead of the official date: The Carmel Tunnels connected to the Krayot Bypass, accessed on November 19, 2026.
- 10Israel Ministry of Transportation and Road Safety, Infrastructure for Growth 2019, accessed on November 19, 2026.
IsraelPedia Question & Answers
What is Highway 22 in Israel?
Highway 22, also known as the Krayot Bypass, is a 14-kilometer highway in the Krayot area near Haifa in northern Israel. It was built to ease congestion in Haifa Bay, providing a signal-free alternative to the congested Histadrut Boulevard section of Highway 4. The highway opened fully in 2013.
Where does Highway 22 run and what does it connect?
Highway 22 extends from Independence Street in Haifa to Kibbutz Ein HaMifratz, linking Haifa’s Lower City with the southern approaches to Acre. Its regional connections include Highway 4, the Carmel Tunnels, the Krayot, Acre, Nahariya, and communities in the Western Galilee.
Why was Highway 22 built?
Highway 22 was intended to relieve heavy traffic on Histadrut Boulevard while serving the Krayot and communities farther north. A construction-stage estimate anticipated a journey of about 15 minutes between Acre and Haifa’s outskirts, compared with 40–50 minutes through the Krayot; this was an expected benefit, not a measured post-opening journey time. By 2018, the road was described as having substantially reduced congestion in the Haifa–Krayot metropolitan area.
What delayed the opening of Highway 22?
A planning condition barred Highway 22 from opening until nearby liquefied petroleum gas storage tanks had been buried. A September 2012 account reported that the High Court of Justice had rejected a petition by three gas companies operating the northern gas farm and required them to bury or relocate the facility.
How was Highway 22 funded and what did it cost?
Highway 22 ultimately proceeded as a contractor-led scheme financed from the state budget as part of an economic stimulus program, rather than as the toll-road, public-private BOT arrangement initially envisaged. In 2009, its estimated overall cost was about NIS 1.9 billion, including approximately NIS 1.2 billion in contracted works and the remainder for land acquisition, compensation, and maintenance. Published figures from other years reflected different stages and scopes of the project.
When did Highway 22 open?
An eight-kilometer section between Yadin Interchange and Bialik Interchange was scheduled to open in September 2012, about six months ahead of plan. By March 2013, the main section from the Technical School area to Kiryat Bialik had opened the previous September, and the final section was due to open in both directions. Highway 22 opened fully in 2013.
Did buses operate on Highway 22?
No buses operated on Highway 22 in 2017. The Transport Ministry explained that the Metronit service on Highway 4 operated as a collector service with an exclusive right-of-way.